Arbitration award received


Company Announcement to the Danish Financial Supervisory Authority No.
35-2013, 4 December 2013.

An ICC (International Chamber of Commerce) arbitration has been concluded in a
case between MT Højgaard A/S and FLSmidth A/S dating back to 2004.

Much to the surprise of FLSmidth and contrary to expectations the ICC
arbitration award renders FLSmidth liable to pay a significant higher
compensation than expected and reserved for.

The arbitration award states that FLSmidth A/S must compensate MT Højgaard A/S
for some of the costs resulting from the delays at the English cement plant
Buxton in 2004.

According to the arbitration award FLSmidth A/S is to pay partial compensation
and interest plus part of the costs of the proceedings to MT Højgaard A/S.

The impact on FLSmidth & Co. A/S' financial statements amounts to a net effect
of approx. DKK -160m on EBITA and DKK -120m on profit after tax, which will be
booked in Q4 2013, and a net cash effect which amounts to approx. DKK -170m.

The Group's guidance for 2013 will be affected by the award. Consequently, the
EBITA margin for 2013 is expected to be 3.5-4.5% (previous guidance 4-5%).


                                 -------------------------------------


Please address any questions regarding this announcement to Group Executive Vice
President and CFO Ben Guren, FLSmidth & Co. A/S at +45 36 18 18 00.

For further information about FLSmidth, please visit www.flsmidth.com.


Yours faithfully

Pernille Friis Andersen
Corporate Communications & Investor Relations