Bruce Power’s Unit 6 connected to Ontario’s electricity grid following Major Component Replacement outage
September 08, 2023 02:09 ET
|
Bruce Power
Tiverton, ON, Sept. 08, 2023 (GLOBE NEWSWIRE) -- Bruce Power’s Unit 6 has been renewed and was connected to Ontario’s electricity grid today following its successful Major Component Replacement...

Bruce Power’s Unit 6 achieves first sustained fission chain reaction, approaches return to service
August 08, 2023 13:02 ET
|
Bruce Power
Tiverton, Ontario, Aug. 08, 2023 (GLOBE NEWSWIRE) -- Bruce Power’s Unit 6 Major Component Replacement (MCR) Project reached a historic milestone over the weekend when the unit achieved a sustained...

Ontario government supports long-term planning and consultation work to explore the expansion of clean nuclear at Bruce Power
July 05, 2023 12:03 ET
|
Bruce Power
Tiverton, Ontario, July 05, 2023 (GLOBE NEWSWIRE) -- Ontario’s Minister of Energy, Hon. Todd Smith, announced support to advance the long-term planning and consultation work required to explore...

Government of Canada teams up with Indigenous partners, Bruce Power and the medical isotope community to fight cancer
June 27, 2023 15:46 ET
|
Bruce Power
Tiverton, Ontario, June 27, 2023 (GLOBE NEWSWIRE) -- The Government of Canada has announced its intent to lead the fight against cancer at home and around the world with funding announced today that...

The Society and Bruce Power reach new deal, members ratify agreement
June 26, 2023 15:19 ET
|
Bruce Power
Tiverton, Ontario, June 26, 2023 (GLOBE NEWSWIRE) -- The Society of United Professionals, IFPTE Local 160, and Bruce Power have reached an agreement to renew their collective agreement. Members of...

Bruce Power signs $1.3 billion fuel channel and feeder replacement contract with Shoreline Power Group for remaining MCR projects
May 11, 2023 16:14 ET
|
Bruce Power
Tiverton, Ontario, May 11, 2023 (GLOBE NEWSWIRE) -- Bruce Power has made a major investment in powering Ontario’s economy and climate change goals forward, awarding a $1.3-billion contract to...

Bruce Power begins loading fuel into Unit 6 reactor as return-to-service activities continue
May 11, 2023 15:21 ET
|
Bruce Power
Tiverton, Ontario, May 11, 2023 (GLOBE NEWSWIRE) -- Bruce Power has commenced loading fuel into Unit 6 and is on track to resume the production of clean, reliable energy and cancer-fighting medical...

Bruce Power Unit 6 MCR construction complete on-time and on-budget
May 04, 2023 14:00 ET
|
Bruce Power
Tiverton, ON, May 04, 2023 (GLOBE NEWSWIRE) -- With the monumental construction phase of the Major Component Replacement portion of its Unit 6 refurbishment now substantially complete, Bruce Power...

Bruce Power issues an additional $600 million in Green Bonds
March 24, 2023 11:39 ET
|
Bruce Power
Tiverton, Ontario, March 24, 2023 (GLOBE NEWSWIRE) -- Bruce Power has issued $600 million in Green Bonds as it continues to help the province and country achieve their Net Zero goals through...

Bruce Power’s begins Unit 3 Major Component Replacement outage
March 02, 2023 10:19 ET
|
Bruce Power
Tiverton, Ontario, March 02, 2023 (GLOBE NEWSWIRE) -- Bruce Power’s Unit 3 was removed from service March 1 to begin its Major Component Replacement (MCR) outage. The refurbished unit is...