FOERSLOEV, Sweden, Jan. 22, 2004 (PRIMEZONE) -- Peab has won the contract to build 129 new flats on the Concordia block in the centre of Malmo. The client is Riksbyggen and the contract amounts SEK 215 million.
Work will begin in March 2004 and moving in will take place in stages from the autumn 2005 till the spring 2006.
The project includes one building along the street with 103 flats and one building in the back yard with 26 flats. Below these buildings, there will be built a garage for the local residents.
For further information contact: Bengt Hansson, Project Manager +46 733 37 40 67 Gosta Sjostrom, Information Manager +46 733 37 10 10
Previous press releases from Peab are available at www.peab.com
This information was brought to you by Waymaker http://www.waymaker.net