TORONTO, Oct. 31, 2018 (GLOBE NEWSWIRE) -- Steppe Gold Limited (TSX: STGO) (the “Company” or “Steppe Gold”) is pleased to announce the progress that has been made over the last month at Altan Tsagaan Ovoo (“ATO”) Gold Project in Mongolia.
CAPITALIZATION TSX Symbol: STGO Total Basic Shares O/S (M): 42.9 BOARD OF DIRECTORS MATTHEW WOOD Chairman, President and CEO BATAA TUMUR-OCHIR Director and Vice President Mongolia ANEEL WARAICH Director and Executive Vice President PATRICK MICHAELS Director DR. ZAMBA BATJARGAL Director LEWIS MARKS Director SHELDON VANDERKOOY Director CONTACT INFORMATION THE COMPANY’S HEAD OFFICE: Shangri-La office, Suite 1201, Olympic street 19A, Sukhbaatar District 1, Ulaanbaatar 14241, Mongolia Tel: +976 7732 1914 TORONTO OFFICE: 90 Adelaide Street. W, Suite 400 Toronto, ON M5H 3V9,Canada Tel: +1 647 697 0577 TRANSFER AGENT: Lori Winchester Senior Relationship Manager, Client Management Phone: +1 416 607-7898 Cell: +1 416 671-4558 Email: lori.winchester@tmx.com | HIGHLIGHTS |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
DEVELOPMENT
The Company is pushing hard for a completion of site construction by the end of 2018 with first gold in the first half of 2019. All materials for the crusher and leach pad have been delivered to site and construction is now underway.
The ATO crushing circuit is nearing construction completion with final work now underway. The crusher will be commissioned initially on mined ATO1 ore in the coming weeks. This material will be used as over liner for the heap leach pads and stacking of the pad should commence over the next month.
Heap leach pad construction is well underway with significant advances being made over the last month. Cell-1 is expected to be completed within the next two weeks and earthwork has now commenced on Cell-2.
Mining camp accommodation and restaurant is fully operational with 106 people on site.
The majority of the ADR plant equipment has been delivered to Mongolia and site works have commenced in preparation for construction next week.
DRA Global has been appointed and has begun to manage and undertake a bankable feasibility study for the construction and development expansion of the ATO Gold Project to 150,000oz gold per annum utilizing a CIL plant for gold and silver production. The study will be based on existing fresh rock ores at ATO1, ATO2 and ATO4, in addition to the potential being seen at the ATO4 – Mungu trend. This study is ongoing.
A selection of photos has been included below demonstrating activities on site:
http://www.globenewswire.com/NewsRoom/AttachmentNg/9b8def2f-d6fe-4491-8c70-e6caf76dfb58
http://www.globenewswire.com/NewsRoom/AttachmentNg/5df5d9e3-f77f-4c46-9d02-8fa753e96a16
http://www.globenewswire.com/NewsRoom/AttachmentNg/b6501782-3f13-41b8-9a7a-aa20708f1e6e
http://www.globenewswire.com/NewsRoom/AttachmentNg/d452a605-b621-4094-898d-808971aec18e
http://www.globenewswire.com/NewsRoom/AttachmentNg/11136a1d-8996-4070-9e75-08845bb78b26
http://www.globenewswire.com/NewsRoom/AttachmentNg/f8c693e1-322d-4b01-99c3-4cb0a1f3f704
http://www.globenewswire.com/NewsRoom/AttachmentNg/e4e4c1d4-d9dd-4513-a7ff-9bcb59a09a68
http://www.globenewswire.com/NewsRoom/AttachmentNg/fd4b9082-a29a-41c5-a3d6-8beddccee586
http://www.globenewswire.com/NewsRoom/AttachmentNg/cc4ef532-468f-44a8-b195-ef2cbc760431
http://www.globenewswire.com/NewsRoom/AttachmentNg/e81e69be-5ff2-43f4-adfa-ec485dde67e4
http://www.globenewswire.com/NewsRoom/AttachmentNg/ba460518-329a-4415-abaa-d86b1c2993f0
http://www.globenewswire.com/NewsRoom/AttachmentNg/d514da8b-ef21-4c9b-b559-2c61ef90f32a
http://www.globenewswire.com/NewsRoom/AttachmentNg/7bf0f804-9556-4643-b5c5-057820468d12
http://www.globenewswire.com/NewsRoom/AttachmentNg/900770f5-173e-400e-9488-27299a9e2cd0
http://www.globenewswire.com/NewsRoom/AttachmentNg/0e6602df-27da-4d47-8992-829fcc681375
http://www.globenewswire.com/NewsRoom/AttachmentNg/d7ac5670-87b0-4353-87a9-4a65a856627e
http://www.globenewswire.com/NewsRoom/AttachmentNg/fe6374e6-0598-4d66-b9f3-4ec9ba20946b
http://www.globenewswire.com/NewsRoom/AttachmentNg/3b32d4a3-5ce0-408b-aa2e-407061a77367
http://www.globenewswire.com/NewsRoom/AttachmentNg/f51baca3-f295-42b6-9377-164cca40dfb8
http://www.globenewswire.com/NewsRoom/AttachmentNg/58ad3dff-dbf4-41e9-bb6f-493d4f434b91
http://www.globenewswire.com/NewsRoom/AttachmentNg/70750852-ab38-46e2-a2a1-06a2776d9846
ATO DRILLING
The Company has now completed a total of 99 drill holes for 16,157.5 meters since acquiring the project in late 2017. Exploration results have been excellent and they demonstrate the high-grade potential of the ATO Gold Project.
The Stage 3 drill program has commenced with three diamond core drilling rigs initially completing the oxide zone drill out at the ATO2 deposit. A total of 752.3 meters in 14 drill holes have been completed by the Company at ATO with results pending.
The Company has now moved all three drilling rigs onto the exciting ATO4 – Mungu trend and to date a total of 3,270.3 meters have been completed in 22 drill holes. This drill program continues to deliver success with visible gold being identified already in ATO-348. This is incredibly encouraging so early in the program with all results pending.
http://www.globenewswire.com/NewsRoom/AttachmentNg/db6f4f5d-f26e-4577-8295-cf3cec26d52e
http://www.globenewswire.com/NewsRoom/AttachmentNg/0561b227-359a-487a-9938-afc5e8c0ef58
http://www.globenewswire.com/NewsRoom/AttachmentNg/fe55e3ce-0f5c-4d9c-9134-2d0b5450a74d
http://www.globenewswire.com/NewsRoom/AttachmentNg/c82f321c-79c1-47a9-9643-9b568eb8d084
The company has also commissioned a structural review report by SRK. This has been completed and has highlighted a number of high-level undrilled targets close to known deposits which have not been drill tested. The first of these targets is expected to be drilled over the coming month.
ABOUT STEPPE GOLD
Steppe Gold is a precious metals exploration and development company with an aggressive growth strategy to build Steppe Gold into the premier precious metals company in Mongolia. The Company owns 100% of the advanced staged Altan Tsaagan Ovoo Gold Project where resource expansion drilling and a heap leach development is currently underway. The Company also owns 80% of the exciting Uudam Khundii Gold Project where an active exploration program is underway and making new discoveries.
Matthew Wood, Executive Chairman said “Over the summer months the Company has experienced some delays to its development schedule from elements outside of the company’s control. These elements are now largely resolved and the Company is proceeding full speed ahead with the ATO mine development. Steppe Gold continues to receive very strong support for the development of the ATO Gold Project from federal, state and local stakeholders in Mongolia with the ATO mine is already adding significantly to the local Soum and Dornod economy.
Steppe Gold is based in Mongolia with its head office in Ulaanbaatar. We are almost entirely staffed by Mongolians and are purely focused on developing precious metals assets in Mongolia. Mongolia is our home. We are extremely proud of the efforts our employees, contractors and consultants are making for shareholders and stakeholders in their efforts to sustainably develop and expand the gold sector in Mongolia. This is already creating increased employment and business opportunities as Steppe Gold grows into the premier precious metals Company in the country. Mongolia is open for business, pro mining development and one of the last great frontiers where giant mineral deposits can be found and developed.”