Jersey, Channel Islands, Aug. 5, 2004 (PRIMEZONE) -- RANDGOLD RESOURCES LIMITED
Incorporated in Jersey, Channel Islands Reg. No. 62686 LSE Trading Symbol: RRS Nasdaq Trading Symbol: GOLD
INTERIM REPORT FOR THE QUARTER AND 6 MONTHS ENDED 30 JUNE 2004
- Net profit for the quarter of US$11.7 million - Sale of Syama concluded - Balance sheet restructured and sub-division of ordinary shares - Loulo Mine development on schedule - Drill results at Yalea reveal broader high-grade payshoots - Decision to proceed with full feasibility on Loulo underground operations - Morila production being returned to planned levels - Good results from Morila exploration and elsewhere
Randgold Resources Limited has 58.5 million shares in issue as at 30 June 2004
CONSOLIDATED INCOME STATEMENT Unaudited Unaudited Unaudited Quarter quarter quarter Ended ended ended 30 June 31 Mar 30 June US$000 2004 2004 2003 Gold sales revenue 12 200 15 274 30 679 Cost of sales Production costs 8 243 8 768 5 243 Transport and refinery costs 46 52 113 Transfer to deferred stripping costs (580) (2 388) 929 Cash operating costs* 7 709 6 432 6 285 Royalties 863 1 079 2 138 Total cash costs* 8 572 7 511 8 423 Profit from mining activity* 3 628 7 763 22 256 Depreciation and amortisation 2 286 2 421 2 224 Exploration and corporate expenditure 4 171 3 016 4 554 (Loss)/Profit from operations* (2 829) 2 326 15 478 Interest received 230 292 445 Interest expense (455) (465) (476) Profit/(Loss) on financial instruments 7 653 (5 847) (52) Profit on sale of Syama 7 070 - - Other income and (expenses) 6 (1 174) 960 Profit on ordinary activities before taxes and minority interests 11 675 (4 868) 16 355 Income tax - - - Minority shareholders' interest - - 195 Net profit 11 675 (4 868) 16 550 Basic earnings per share (US$) 0.20 (0.08)+ 0.30+ Fully diluted earnings per share (US$) 0.20 (0.08)+ 0.29+ Average shares in issue (000) 58 547 58 524+ 56 148+ CONSOLIDATED INCOME STATEMENT cont'd Unaudited Unaudited 6 months 6 months ended ended 30 June 30 June US$000 2004 2003 Gold sales revenue 27 474 62 265 Cost of sales Production costs 17 011 11 764 Transport and refinery costs 98 228 Transfer to deferred stripping costs (2 968) 556 Cash operating costs* 14 141 12 548 Royalties 1 942 4 345 Total cash costs* 16 083 16 893 Profit from mining activity* 11 391 45 372 Depreciation and amortisation 4 707 4 537 Exploration and corporate expenditure 7 187 7 364 (Loss)/Profit from operations* (503) 33 471 Interest received 522 516 Interest expense (920) (1 018) Profit/(Loss) on financial instruments 1 806 (328) Profit on sale of Syama 7 070 - Other income and (expenses) (1 168) 741 Profit on ordinary activities before taxes and minority interests 6 807 33 382 Income tax - - Minority shareholders' interest - 274 Net profit 6 807 33 656 Basic earnings per share (US$) 0.12 0.60 Fully diluted earnings per share (US$) 0.12 0.59 Average shares in issue (000) 58 547 56 148
* Refer to pro forma information provided on page three. + Reflects adjustments resulting from sub-division of shares.
CONSOLIDATED CASH FLOW STATEMENT Unaudited Unaudited 6 months 6 months ended ended 30 June 30 June US$000 2004 2003 Net cash generated from operations 5 450 34 886 Net cash utilised in investing activities Additions to property, plant and equipment (21 776) (1 544) Proceeds on disposal of Syama 8 634 - Other investing activities (3 993) - Net cash (utilised in)/generated by financing activities Ordinary shares issued 58 6 763 Decrease in long-term borrowings (9 162) (4 416) (Decrease)/Increase in bank overdraft (1 550) 169 Net (decrease)/increase in cash and cash equivalents (22 339) 35 858 Cash and cash equivalents at beginning of period 105 475 59 631 Cash and cash equivalents at end of period 83 136 95 489 CONSOLIDATED BALANCE SHEET Unaudited Unaudited Audited At at at 30 June 30 June 31 Dec US$000 2004 2003 2003 Assets Cash and equivalents** 83 136 100 035 109 357 Receivables 16 907 10 288 15 196 Inventories 13 941 13 968 17 165 Total current assets 113 984 124 291 141 718 Property, plant and equipment Cost 196 971 170 980 175 195 Accumulated depreciation (107 080) (96 641) (102 373) Net property, plant and equipment 89 891 74 339 72 822 Other long-term assets 14 512 6 846 10 885 Total assets 218 387 205 476 225 425 Bank overdraft - 1 339 1 550 Accounts payable and accrued liabilities 14 945 15 631 23 557 Total current liabilities 14 945 16 970 25 107 Provision for environmental rehabilitation 3 552 5 115 5 962 Liabilities on financial instruments 4 680 5 613 8 488 Long-term loans 7 439 15 037 7 723 Loans from outside shareholders in subsidiaries 1 343 1 036 958 Total long-term liabilities 17 014 26 801 23 131 Total liabilities 31 959 43 771 48 238 Shareholders' equity 186 428 161 705 177 187 Total liabilities and shareholders' equity 218 387 205 476 225 425
** Note: These amounts include US$4 546 at 30 June 2003 and US$3 882 at 31 December 2003 respectively which relate to the N.M. Rothschild & Sons Limited debt service reserve account.
CONSOLIDATED STATEMENT OF CHANGES IN EQUITY Number of Share Share ordinary capital premium shares US$000 US$000 Balance - 31 Dec 2002 27 663 740 2 766 190 618 March 2003 quarter Net profit - - - Movement on cash flow hedges - - - Share options exercised 471 926 47 1 665 June 2003 quarter Net profit - - - Movement on cash flow hedges - - - Share options exercised 574 362 57 4 994 Balance - 30 June 2003 28 710 028 2 870 197 277 Balance - 31 December 2003 29 260 385 2 926 200 244 March 2004 quarter Net loss - - - Share options exercised 3 000 - 13 Share split (a) 29 263 385 - - Capital reduction (b) - - (100 000) June 2004 quarter Net Profit Movement on cash flow hedges Share options exe 20 600 1 44 Balance - 30 June 2004 58 547 370 2 927 100 301 CONSOLIDATED STATEMENT OF CHANGES IN EQUITY (cont'd) Accumula- Other ted profit/ Total Reserves (losses) equity US$000 US$000 US$000 Balance - 31 Dec 2002 (8 293) (66 106) 118 985 March 2003 quarter Net profit - 17 106 17 106 Movement on cash flow hedges 2 059 - 2 059 Share options exercised - - 1 712 June 2003 quarter Net profit - 16 550 16 550 Movement on cash flow hedges 242 - 242 Share options exercised - - 5 051 Balance - 30 June 2003 (5 992) (32 450) 161 705 Balance - 31 December 2003(7 403) (18 580) 177 187 March 2004 quarter Net loss - (4 868) (4 868) Share options exercised - - 13 Share split (a) - - - Capital reduction (b) - 100 000 - June 2004 quarter Net Profit 11 675 11 675 Movement on cash flow hedges 2 376 2 376 Share options exercised 45 Balance - 30 June 2004 (5 027) 88 227 186 428
(a) Share split: A special resolution was passed on 26 April 2004 to split each of the ordinary shares of US$0.10 in the Company into two ordinary shares of US$0.05 each. The aim was to improve the tradability of the Company's shares and to equalise a share's value before and after the share split.
(b) Capital reduction: A special resolution was passed at the Annual General Meeting in April 2004, which was subsequently approved by the Court in Jersey, to extinguish accumulated losses by reducing the Company's share premium account by US$100 million in order to clear the way for future dividend payments.
PRO FORMA INFORMATION
The Company uses the following pro forma disclosures as it believes that this information is relevant to the mining industry.
Total cash costs per ounce are calculated by dividing total cash costs, as determined using the Gold Institute Industry Standard, by gold ounces produced for all periods presented.
Total cash costs as defined in the Gold Institute Industry Standard, includes mine production, transport and refinery costs, general and administrative costs, movement in production inventories and ore stockpile, transfers to and from deferred stripping and royalties.
Cash operating costs are defined as total cash costs excluding royalties.
Total cash operating costs per ounce are calculated by dividing cash operating costs by gold ounces produced for all periods presented.
Profit from mining activity is calculated by subtracting total cash costs from gold sales revenue for all periods presented.
Profit from operations is calculated by subtracting depreciation and amortisation charges and exploration and corporate expenditure from profit from mining activity.
RECONCILIATION TO US GAAP
The interim condensed financial statements presented above have been prepared in accordance with International Financial Reporting Standards (IFRS), which differ in certain significant respects from Generally Accepted Accounting Principles in the United States (US GAAP). The effect of applying US GAAP to net income and shareholders' equity is set out below.
6 months 6 months 30 June 30 June Reconciliation of net income (US$000) 2004 2003 Net income under IFRS 6 807 33 656 Share option compensation adjustment 253 (1 717) Net income under US GAAP before cumulative effect of change in accounting principle 7 060 31 939 Cumulative effect of change in accounting principle - net of tax - 214 Net income under US GAAP 7 060 32 153 Movement in cash flow hedges during the period 2 376 2 301 Comprehensive income under US GAAP 9 436 34 454 Basic earnings per share under US GAAP (US$)* 0.16 0.57 Fully diluted earnings per share under US GAAP (US$)* 0.16 0.56 Reconciliation of shareholders' equity (US$000) Shareholders' equity under IFRS 186 428 161 705 Shareholders' equity under US GAAP 186 428 161 705 Roll forward of shareholders' equity under US GAAP Opening balance 177 187 118 771 Net income under US GAAP 7 060 32 153 Movement on cash flow hedges 2 376 2 301 Share options exercised 58 6 763 Share option compensation adjustment (253) 1 717 Shareholders' equity under US GAAP closing balance 186 428 161 705
* Reflects adjustments resulting from sub-division of shares.
ACCOUNTING POLICIES
The interim condensed financial statements in this report have been prepared in accordance with the Group's accounting policies, which are in terms of International Financial Reporting Standards and are consistent with the prior period.
The consolidated financial information includes the interim financial statements of the Company, its subsidiaries and the Morila joint venture, which comply with IAS 34.
Joint ventures are those investments in which the Group has joint control and are accounted for under the proportional consolidation method and under this method, the proportion of assets, liabilities, income and expenses and cashflows of each joint venture attributable to the Group are incorporated in the consolidated financial statements under appropriate headings. Inter-company accounts and transactions are eliminated on consolidation.
No segmental information has been provided as the source and nature of the enterprises, risks and returns are not governed by more than one segment.
FINANCIAL INSTRUMENTS
Morila
The financial instruments at 30 June 2004 held by the Morila company are the remainder of derivatives taken out as part of the project finance arrangements. Randgold Resources' attributable share is as follows:
- 25 971 ounces sold forward at a fixed price of US$275/oz over the period July 2004 to December 2004;
- 9 192 ounces of call options purchased at a price of US$360/oz over the same period.
At present prices, the percentage of attributable production which is hedged is approximately 17% for the next six months. By December 2004 Morila will be unhedged.
Loulo
As disclosed last quarter, the Loulo price protection was initially done at a Randgold Resources level, on a short dated spot deferred basis. With the completion of the final mining schedules and feasibility study, as well as credit approval of the project financing, the hedged ounces have now been rolled out and matched to future production.
- 300 000 ounces sold forward at a fixed price of US$430/oz over the period July 2005 to December 2009 in line with the mining schedules.
- A further 25 000 ounces of gold hedges at US$405/oz were acquired in July 2004 in accordance with board approval. These ounces have been sold forward on a spot deferred basis and will in due course be rolled out and matched to future production.
Marked-to-market valuation
Movements in marked-to-market valuations of financial instruments can be accounted for in two ways, either through the income statement or directly to reserves, depending on the nature of the instrument. The Morila instruments are accounted for mainly on a hedge basis i.e. are matched to production and movements on the marked-to-market valuation are, therefore, accounted for in reserves. The Loulo instruments were previously deemed speculative for accounting purposes and any marked-to-market movements had to be accounted for through the income statement. These instruments have now been matched to planned Loulo production, the contango has been applied and are now deemed hedges. This means that the marked-to-market valuation is now accounted for in reserves.
COMMENTS
Profit from mining activity* for the quarter of US$3.6 million was lower than the previous quarter's US$7.8 million. Ounces produced were 85 081 compared to 107 115 in the previous quarter. This is partly due to the mine plan which scheduled lower production for the quarter and which was further exacerbated by operational issues resulting in a reduction in metallurgical recovery.
Production levels are scheduled to pick up later in the year with higher grade ore being accessed and the mine operator addressing the problems of throughput and recoveries. Morila's production for the year is now expected to be lower than previously forecast at 500 000 ounces.
Exploration and corporate expenditure of US$4.2 million, up 38% from the previous quarter, was in line with the same period last year and reflects the Group's continued commitment to exploration. Depreciation of US$2.3 million was in line with the previous quarter. The profit on financial instruments of US$7.7 million is a result of closing out the fixed rate agreements at the end of June 2004 and the roll-forward of the forward sales to match anticipated future production. This is a non cash item resulting from the marked-to-market valuation of the hedging transactions entered into as part of the Loulo project financing. The forward sales were previously classified as speculative for accounting purposes and accounted for through the income statement. The forward sales have now been matched to production, are deemed hedges and are, therefore, now accounted for in reserves.
A profit of US$7.1 million was realised on the conclusion of the sale of Syama to Resolute Mining Limited. This excludes the future royalty payments and is net of sale costs.
The net profit for the quarter of US$11.7 million reflects a positive variance of US$16.5 million compared to the previous quarter net loss of US$4.9 million. Net profit was US$16.6 million in the corresponding quarter in 2003, mainly due to the very high grades being processed at Morila at that time.
The main movements on the balance sheet are a decrease in the cash and cash equivalents. This is mostly attributable to the financing of the Loulo capital project which is being funded by the Company prior to the finalisation of the project finance. The final payment of the Morila Project Loan which was made at the end of June 2004, also contributed to the reduction in cash and cash equivalents. This was offset by the cash received from the sale of Syama.
Net profit for the six months ended 30 June 2004 of US$6.8 million compared to US$33.7 million for the corresponding period in 2003 reflects the impact of the higher grade mined in the high-grade axis in the Morila pit as previously reported.
OPERATIONS MORILA
Morila results Quarter Quarter ended ended 30 June 31 Mar US$000 2004 2004 Mining Tons mined (000) 5 261 6 605 Ore tons mined (000) 889 887 Milling Tons processed (000) 867 795 Head grade milled (g/t) 3.8 4.9 Recovery (%) 80.0 86.0 Ounces produced 85 081 107 115 Average price received (US$/ounce) 348 369 Cash operating costs* (US$/ounce) 213 160 Total cash costs* (US$/ounce) 238 185 Cash profit (US$000) 9 070 19 408 Attributable (40%) Ounces produced 34 032 42 846 Cash profit (US$000) 3 628 7 763 Morila results (cont'd) Quarter 6 Months 6 Months ended ended ended 30 June 30 June 30 June US$000 2003 2004 2003 Mining Tons mined (000) 5 389 11 886 11 345 Ore tons mined (000) 1 273 1 776 2 496 Milling Tons processed (000) 771 1 662 1 601 Head grade milled (g/t) 10.5 4.3 10.1 Recovery (%) 90.9 83.2 91.3 Ounces produced 236 449 192 196 474 870 Average price received (US$/ounce) 337 360 338 Cash operating costs* (US$/ounce) 70 183 67 Total cash costs* (US$/ounce) 93 208 90 Cash profit (US$000) 55 640 28 478 113 430 Attributable (40%) Ounces produced 94 580 76 878 189 948 Cash profit (US$000) 22 256 11 391 45 372
* Refer pro forma information provided above.
Tons milled increased over the previous quarter and indications are that the milling circuit is starting to reach its expansion design throughput. The additional CIL tanks have been commissioned but the commissioning of the thickener and the new tailings disposal was delayed.
Operational problems caused by difficulties in integrating the expansion project reduced throughput and recoveries below planned levels and had a negative impact on the results for the quarter. The main problems were:
- an unstable milling and grinding performance, which produced a coarser than planned grind;
- two CIL tanks were offline for extended periods due to mechanical difficulties, with consequently lower residence times; and
- unscheduled shutdowns of the pre-CIL circuit, which led to reduced plant availability.
Correcting the operational inefficiencies in order to return the mine to planned performance levels is now management's main priority. Randgold Resources and its joint venture partner AngloGold Ashanti have developed a technical action plan and timetable designed to achieve this as a matter of urgency. The operator is committed to implementing this plan and its progress will be reviewed at short intervals by the two partners' senior managements.
While it is expected that there will be a significant improvement in the third quarter, the poor operational performance of the first two quarters has resulted in expected production for 2004 being revised downwards to 500 000 ounces.
A three day work stoppage related to demands for a productivity bonus occurred during June. Discussions with the unions are continuing.
Exploration to the northwest of the current pit has returned encouraging results which indicate the potential for a significant extension of the Morila orebody. An envelope of mineralised material estimated to contain 900 000 ounces has been outlined by a wide spaced drilling programme. Further infill drilling to upgrade this resource has been approved.
SALE OF SYAMA
In April 2003, the Company entered into an option agreement with the Australian mining company, Resolute Mining, over its interest in the Syama Mine in Mali. In terms of the agreement, Resolute Mining was given a 12 month period in which to conduct a full due diligence over Syama.
On 5 April 2004, Resolute Mining exercised its option to buy the Company's 80% interest in the Syama Mine. In terms of the option, Resolute Mining paid the Company US$6 million and has assumed current liabilities of US$7 million of which US$2.74 million was owing to Randgold Resources. Furthermore, at a gold price of more than US$350 per ounce, the Company would receive a royalty of US$10 per ounce on the first million ounces of production from Syama and US$5 per ounce on the next three million ounces based on the attributable ounces acquired by Resolute Mining. This has not been included in the profit attributable to the sale of Syama, as it is dependent on the mine producing gold in future and that a minimum gold price of US$350 per ounce be achieved.
The Group received net proceeds of US$8.6 million on the sale and made a profit of US$7.1 million.
PROJECTS AND EVALUATION
Loulo Project
Work continued apace on the development of the project. Design activities are nearing completion and procurement of equipment and materials is well advanced. The main construction contract with MDM has been agreed and construction is progressing rapidly. The mining contract is being finalised and a letter of intent has been issued to Bayswater Construction & Mining. The power generation contract has been reduced to two contenders and will be finalised in August 2004.
Site progress is good. The plant water supply has been secured with the completion of the Faleme weir. Plant ground clearing is complete and terracing is 50% finalised. Excavations and earthworks are complete. Aggregate crushing and concrete batching facilities are operational. There are approximately 700 construction personnel on site. Civils are on schedule and key concrete foundations are above terrace level ahead of the rainy season.
90km of older access roads have been resurfaced and a further 30km of new gravel roads established to secure access to the site through the rainy season. The project is on track for commissioning and production by mid 2005.
The US$60 million project financing is nearing completion. All terms have been agreed with the banks and the technical audit by RSG Global has been completed. Final documentation involving the Mali Government is being concluded.
Results from the underground prefeasibility study carried out by SRK Consulting are positive and SRK will now proceed to complete the full feasibility study. The study confirms the potential for development of long life underground operations exploiting the extensions to the Loulo 0 and Yalea orebodies and a further infill drilling programme has been approved.
Tongon Project
The situation in the Cote d'Ivoire is being monitored. The Company has maintained its presence in the country and is capable of recommencing feasibility and exploration work without delay once the political and security situation returns to acceptable levels.
EXPLORATION ACTIVITIES
During the quarter, an intense exploration campaign progressed with the completion of programmes in West Africa prior to the commencement of the annual rains, while in East Africa, operations were initiated following a generative phase. The following activities were effected:
- Aggressive drilling continued at Loulo with focus on testing continuations of high-grade payshoots at Yalea;
- Drilling continued on the Morila joint venture focusing on the western margin of the orebody and conceptual exploration targets;
- In the Morila region surface work and ground geophysics have highlighted eight new targets for drill testing after the current rainy season;
- Reconnaissance drilling commenced on the Senegal portfolio;
- In Ghana on the Adansi Asaasi joint venture soil sampling, field mapping and adit identification have been completed on 37% of the permit area;
- In Tanzania exploration focuses on steep and flat mineralisation similar to that being exploited by Placer Dome on the adjoining permits within the Mara Belt while in the Musoma area trenching highlighted new surface mineralisation; and
- In Burkina Faso a plus two kilometre gold bearing shear zone is being explored on the Danfora Permit.
At the Yalea deposit within the Loulo Project area a further 24 deep holes were drilled covering a plus two kilometre strike length. Excellent results have been received down to a maximum vertical depth of 640 metres returning values of up to 23.97g/t over widths of 3.7 to 52 metres (Table 1). This includes a plus 800 metre strike length of very high grade averaging 12g/t over a width of 15.6 metres and the identification of numerous high-grade payshoots not coming to surface. As part of the underground prefeasibility study, future infill and deep drilling have been evaluated and the next phase of infill drilling approved. Follow-up surface exploration work along the Yalea structure confirmed continuation of the zone of mineralisation southwards for a further two kilometres. Four reconnaissance diamond holes were drilled to test the structure and returned encouraging intercepts of 19 metres at 1.4g/t, 8 metres at 2.7g/t and 5 metres at 2.8g/t. Similarly, modelling to the north of Yalea - P125 confirmed 13 new dilational areas along a ten kilometre strike length which will be the focus of continued generative work. A diamond hole was recently completed to test the first of these and intersected multiple zones of mineralisation between 85 and 120 metres vertical depth below the surface.
Table 1: Deep drilling results along the Yalea Structure
Area Northing ID From To Width Inter- section P125 1443170 P125DH20 255 267 12 12m @ 9.80g/t P125 1443127 P125DH18 186 199 13 13m @ 2.45g/t P125 1443044 P125DH17 242 274 32 32m @ 1.70g/t including 242 250 8 8m @ 2.59g/t including 265 274 9 9m @ 2.62g/t Yalea 1442940 YDH152 326 348.25 22.25 22.25m @ 7.48g/t Yalea 1442859 YDH151 339 352 13 13m @ 7.45g/t Yalea 1442782 YDH134 471 475.48 4.48 4.48m @ 1.99g/t Yalea 1442675 YDH149 459 486 27 27m @ 6.03g/t including 459 473 14 14m @ 8.58g/t Yalea 1442575 YDH150 487 531 44 44m @ 2.62g/t including 487 517 30 30m @ 3.29g/t Yalea 1442470 YDH132 487 538 51 51m @ 10.86g/t Yalea 1442386 YDH141 547 572 25 25m @ 13.45g/t Yalea 1442284 YDH140 619 630 11 11m @ 20.14g/t Yalea 1442153 YDH142 546 550 4 4m @ 10.21g/t Yalea 1442010 YDH136 586.4 590.1 3.7 3.7m @ 23.97g/t Yalea 1441950 YDH143 616.72 624 7.28 7.28m @ 18.47g/t Yalea 1441828 YDH137 501 514 13 13m @ 1.69g/t Yalea 1441732 YDH144 634 639 5 5m @ 5.96g/t Yalea 1441663 YDH145 742.9 755 12.1 12.1m @ 6.70g/t Yalea 1441499 YDH146 650 668 18 18m @ 3.62g/t including 652 659 7 7m @ 3.18g/t and 675 685 10 10m @ 4.71g/t Yalea 1441386 YDH147 582 609 27 27m @ 10.62g/t including 583 601 18 18m @ 14.57g/t Yalea 1441336 YDH126 368 394 26 26m @ 2.66g/t including 373 379 6 6m @ 6.80g/t Yalea 1441266 YDH148 644 706 62 62m @ 1.51g/t including 646 653 7 7m @ 3.61g/t Yalea 1441237 YDH130 375 377 2 2m @ 4.41g/t and 408 411 3 3m @ 1.10g/t
At Morila Mine, following completion of the near mine geological model, further drilling was undertaken on the northwest margin of the pit and returned multiple flat lying mineralised zones with intercepts of between 4 and 33 metres at grades of 3 to 8g/t. A resource estimate has been completed as referenced in the Morila section. In the Domba - Morila corridor, the first compartment was drilled and confirmed the geological model intersecting flat lying mineralisation. A further eight conceptual drill targets will be tested.
Following the modelling of a conceptual anticlinal target situated west of the main pit, reconnaissance drilling has intersected significant mineralisation in two boreholes 800 metres west of the pit. The mineralised anticlinal structure trends in a similar direction to the high-grade axis of the main Morila orebody. The two boreholes are located 160 metres apart and intersect broad zones of mineralisation. Both intersections include high grade intervals (5 metres @ 31g/t and 4 metres @ 36g/t) at depths of approximately 350 metres below surface. Additional boreholes are planned to further evaluate this target.
Outside the Morila joint venture, but within the Morila region, eight new targets with similar compartment settings have been identified from ground geophysics and field work and will be drill tested after the rainy season.
In Senegal, a reconnaissance diamond drilling programme commenced with the testing of two targets and will continue after the annual rains. On the TA target within the Tomboronkoto permit, four diamond holes confirmed the geometry defined by surface trenching and continuity of mineralisation over an 800 metre strike within a granodiorite intrusion. At Bambaraya, on the Kounemba permit, five diamond holes confirmed mineralisation over two kilometres along a five kilometre structural corridor, this new data together with the higher grade trench results will enable modelling to define future work programmes.
In Ghana, good progress has been made on the Adansi Asaasi joint venture with the collection of 2 398 soil samples, field mapping and adit identification completed on the potential north eastern extensions to the Obuasi structural corridor. The first 500 soil results have been returned and indicate anomalous values up to 2.3g/t associated with the contact between Birrimian sediments and metavolcanics.
In Tanzania, within the Mara Belt, we have three licences on the eastern extensions to the gold bearing structures which host the Nyabirama, Nyabigena and Gokona ore deposits of East African Gold Mines. These structural corridors will be the focus of detailed ground IP surveys to target below cover basalts. At the Mughusi target gold bearing vein systems are hosted within an altered granodiorite.
In the Musoma Belt, we hold the dominant land position with 13 licences covering the area between Buhemba mine and the Kiabakari prospect. Trenching has returned values of 1.4 to 2.3g/t over widths of between 42 and 56 metres associated with a sheared and altered Banded Iron Formation (BIF) unit on the Kiabakari East permit. The BIF unit is associated with coincident shearing, soil and aeromagnetic anomalies for a further three kilometres to the east-southeast. Follow up work is in progress along this target zone.
In Burkina Faso, on the Danfora permit a ground magnetic survey covering a five kilometre strike along the previously identified shear zone has been completed and results clearly identify the main structure and basalts hosting mineralisation. Mineralisation styles show similarities to the five million ounce resources of Syama. Data integration is currently in progress to define drill locations.
On the recently acquired Kiaka permit, reconnaissance exploration identified a major northeast trending structural zone referred to as the Markoye fault which can be traced through the permit area for over 20 kilometres. Gold mineralisation is associated with altered schists in contact with foliated intrusive rocks. Exploration work will commence after the rainy season.
CORPORATE AND NEW BUSINESS
In Tanzania, the Company has extended its presence in the Musoma and Mara regions through a joint venture agreement with Barrick and now holds 19 licences in the country. The Company can earn a 50% participatory interest in the joint venture with Barrick, which covers five permits, by expending a minimum of US$300 000 in year one and completing a Type III Feasibility study on the first discovery. If Barrick elect not to follow their rights after Type III then Randgold Resources can go to 70% by completing a Type IV Feasibility Study.
In Burkina Faso, a second permit referred to as Kiaka has been acquired, located in the south of the country.
Along with several other interested parties, the Company was invited by the Government of Senegal to submit an offer to develop the Sabodala Project. We submitted our bid on time and now await the results of the adjudication process.
The Company continues to look at a number of opportunities both at a corporate and project level. As has been stated in the past, value creation in the mining industry is best achieved through discovery and development. Notwithstanding the fact that we continue to search for value or strategic leverage in merger and acquisition opportunities, Randgold Resources has been consistent in its belief in organic growth through exploration.
D M Bristow R A Williams Chief Executive Financial Director 5 August 2004
Download a pdf (acrobat format) copy of this announcement from : http:// www.randgoldresources.com/cws/mvcServlet/cws.bpc.Catalogue/showListByTypeName? project_name=randgold&product_type_name=quarterly_reports
Registered office:
La Motte Chambers, La Motte Street, St. Helier, Jersey JE1 1BJ, Channel Islands
Web-site: www.randgoldresources.com
Registrars:
Computershare Investor Services (Channel Islands) Limited, PO Box 83, Ordnance House, 31 Pier Road, St. Helier, Jersey JE4 8PW, Channel Islands
Transfer agents:
Computershare Services plc, PO Box 663, 7th Floor, Jupiter House, Triton Court, 14 Finsbury Square, London EC2A 1BR
DISCLAIMER: Statements made in this document with respect to Randgold Resources' current plans, estimates, strategies and beliefs and other statements that are not historical facts are forward-looking statements about the future performance of Randgold Resources. These statements are based on management's assumptions and beliefs in light of the information currently available to it. Randgold Resources cautions you that a number of important risks and uncertainties could cause actual results to differ materially from those discussed in the forward-looking statements, and therefore you should not place undue reliance on them. The potential risks and uncertainties include, among others, risks associated with: fluctuations in the market price of gold, gold production at Morila, the development of Loulo and estimates of reserves and mine life. For a discussion on such risk factors, refer to the annual report on Form 20-F for the year ended 31 December 2003, which was filed with the Securities Exchange Commission on 30 June 2004. Randgold Resources assumes no obligation to update information in this release. Cautionary Note to US Investors: The United States Securities Exchange Commission (the 'SEC') permits companies, in their filings with the SEC, to disclose only proven and probable ore reserves. We use certain terms in this release, such as "resources", that the SEC does not recognise and strictly prohibits us from including in our filings with the SEC. Investors are cautioned not to assume that all or any part of our resources will ever be converted into reserves which qualify as 'proven and probable reserves' for the purposes of the SEC's industry guide number 7.
This information is provided by RNS The company news service from the London Stock Exchange