This IT Notice contains launch time schedule for Genium INET (Derivatives, Fixed Income, Commodities).
As previously communicated, Nasdaq is in the process of relocating its primary data center from the current LUNDA data center to the new VASBY data center. This relocation affects all customers, service- and connectivity providers with connectivity to LUNDA and PORT data centers.
Furthermore a new Genium INET (Derivatives, Fixed Income, Commodities) trading and clearing platform has been built at VASBY and PORT, replacing the current Genium INET platform at LUNDA and PORT data centers on June 20th, 2016. Customers that have not adapted to new IP´s and ports by June 20th will not be able to access the Derivatives, Fixed Income or Commodities market.
Genium INET (Derivatives, Fixed Income, Commodities) Production Launch time schedule
Saturday June 18th, 14:00 – 17:00 (CEST) – Final login verification test
- New Genium INET in VASBY launched as the Primary Production Site
- New Genium INET in PORT launched as the Secondary Production Site
- “Old” Genium INET environments in LUNDA and PORT are discontinued (no logins or ITCH MC services)
- Customer login verification test will be arranged on Saturday June 18th between 14:00 – 17:00 CEST
- No markets open (only heartbeats to verify ITCH MC connections)
- Please send us a confirmation via e-mail to technicalrelations@nasdaq.com, as soon as you have completed your Genium INET migration from LUNDA to VASBY data center and verified login (latest by June 18th, 17:00 CEST)
Monday June 20th -> Launch
- New Genium INET in VASBY live as the Primary Production site
- New Genium INET in PORT live as the Secondary Production site
- Genium INET Data Center Relocation completed
Additional information regarding Genium INET (Derivatives, Fixed Income, Commodities)
- Genium INET VASBY and PORT connectivity information is available at the Data Center Relocation website
- Members’ individual FIX port information has been distributed to all clients. If you haven’t received the new connectivity details please contact ms.gi@nasdaq.com
- Members accessing Genium INET ports from new source IP’s/subnets need to inform ms.gi@nasdaq.com about the new details (source IP validation)
- Derivatives and Fixed Income customers should remove all their long orders by market close on June 17th. After market close, order books will be flushed and remaining orders will be removed without sending out a cancel message
- Detailed Launch Weekend Plan will be published on Monday June 13th, 2016
Data Center Relocation website:
http://www.nasdaqomx.com/transactions/technicalinformation/data-center-relocation
For Technical issues and questions, please contact:
Technical Support
technicalsupport@nasdaq.com
+46 8 405 6750
For Account/Port configurations, please contact:
Member Services
ms.gi@nasdaq.com
+46 8 405 6660
| For questions regarding this IT-Notice, please contact: | |||
|
Charlie Holmgren Market Readiness Genium INET charlie.holmgren@nasdaq.com or technicalrelations@nasdaq.com +46 8 405 6944 |
|||
Best regards,
Nasdaq Nordic and Nasdaq Baltic
Nasdaq Copenhagen, Nasdaq Helsinki, Nasdaq Iceland, Nasdaq Riga, Nasdaq Stockholm, Nasdaq Tallinn and Nasdaq Vilnius are respectively brand names for Nasdaq Copenhagen A/S, Nasdaq Helsinki Ltd, Nasdaq Iceland hf., Nasdaq Riga AS, Nasdaq Stockholm AB, Nasdaq Tallinn AS and AB Nasdaq Vilnius. Nasdaq Nordic represents the common offering by Nasdaq Copenhagen, Nasdaq Helsinki, Nasdaq Iceland and Nasdaq Stockholm. Nasdaq Baltic represents the common offering by Nasdaq Tallinn, Nasdaq Riga and Nasdaq Vilnius.